For some tasks, the parent shows a percentage (e.g. 5%), others just a number (e.g. 0.9) (see attached). If I add new rows, the % shows, but I see no method to change the format of the non-% ones. Any ideas please.
Did you apply formatting to the entire column?
That can't be done as the column is locked by Project Settings due to activating dependency settings.
Damn, I rechecked and now the % format option is accessible. I clicked and problem solved.. Thanks for the pointer back to that.
I would check and make sure your dependencies are turned on as you indicated they were. I'm glad we got that problem solved!
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…