Sign in to join the conversation:
For some tasks, the parent shows a percentage (e.g. 5%), others just a number (e.g. 0.9) (see attached). If I add new rows, the % shows, but I see no method to change the format of the non-% ones. Any ideas please.
Did you apply formatting to the entire column?
That can't be done as the column is locked by Project Settings due to activating dependency settings.
Damn, I rechecked and now the % format option is accessible. I clicked and problem solved.. Thanks for the pointer back to that.
I would check and make sure your dependencies are turned on as you indicated they were. I'm glad we got that problem solved!
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
I have an automation setup to escalate to managers when a step goes beyond 2 days. I have that titled as Escalation for Purchasing, Escalation for Planning, etc. In my trial run, 3 out of 6 showed up as Reminder: New part number request log ( this is the name of the sheet) The only thing we could see was that the ones that…