I have a project where the planned tasks are spread over several weeks, see attached.
How is the summary % complete total calculated? Can I relate to %complete against project days?
Regards
Steve
The summary % Complete is an average of the children.
Can you explain in more detail what you mean by "Can I relate to %complete against project days"?
Hi Paul,
Thanks for your reply. From my example 44% complete implies 1.10 days completed in the project. However, project days x %complete gives 1.15. Is this correct? Because my project days are spread over a longer durations, what the best way to represent the %complete?
Regards Steve
That depends on the level of accuracy you are looking for. the 0.05 days difference relates to 1 hour and 12 minutes difference.
Also... What is the difference between the Project Days and the Duration?
I'm just struggling to figure out exactly how your process is working.
Project days are the days sold to the client for the delivery of a task. However, this may be spread over weeks which gives a longer duration in smartsheet, e.g. 18/08/19 to 28/08/19 gives 9d duration but the time spend on the project is 1 day spread over the 9d.
So could it also be said that the duration is 1 day with 8 days lag or lead time?
Hi Paul, that's correct. However, the nature of our construction projects is that 1 day is schedule over 2 weeks but we not sure when the work would actually be done so the plan shows the duration as 10 days against 1 project day. Regards Steve
You would need to be able to build in actual start and finish dates and run your % Complete off of those then.
Hi Paul, OK, thank you, regards Steve
Happy to help!
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…
I have a picture below for an example of this. I want to create a formula to get counts of items in "Column2", but if "Column4" states "change" I want the "Column2" count to not work and instead count what is it "Column3" in that given row. Column4 can also have several different things in it besides "good" that I want it…
I've done this a million times - create a report, separated by campus with a total $$. Then add it to a dashboard and make a graph. NOTHING is working right now when I try to do this. I get an error that the data cannot be charted. What the what? Help anyone? Is this a issue since they apparently changed something in the…