Hi,
I would like to see a view/report/grid (something) that displays the overall effort and cost per month per project eg
Project A
Jan l 700hrs l £7000
Feb l 500hrs l £5000
Mar l 300hrs l £3000
ETC......
Is there anyway of seeing this?
Thanks Liz
Hi Liz,
Yes, probably.
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Hi Andrée,
Not sure if this screenshot is helpful but basically for each month eg October I want to see how much effort is planned in so that I can work out the predicted cost for each month
Cheers Liz
Are you using the same duration measurements? We must use that because then we can calculate the duration.
Would that work?
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…
I have a picture below for an example of this. I want to create a formula to get counts of items in "Column2", but if "Column4" states "change" I want the "Column2" count to not work and instead count what is it "Column3" in that given row. Column4 can also have several different things in it besides "good" that I want it…
I've done this a million times - create a report, separated by campus with a total $$. Then add it to a dashboard and make a graph. NOTHING is working right now when I try to do this. I get an error that the data cannot be charted. What the what? Help anyone? Is this a issue since they apparently changed something in the…