Sign in to join the conversation:
I cannot figure out why this formula does not work. HELP! Thanks.
Suggestions:
=IF([Complete]1 = 1, "B"),
IF([Finish]1< TODAY, "R"),
IF([Finish]1 >= TODAY(+45), "Y"),
IF([Finish]1 <= TODAY(+90), "G", " ")))
Hi,
Are you trying to use the RYGB Symbols? Do you get an error message?
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Try something like this.
=IF(Complete@row = 1; "Blue"; IF(ISBLANK(Finish@row); ""; IF(Finish@row < TODAY(); "Red"; IF(Finish@row >= TODAY(45); "Yellow"; IF(Finish@row <= TODAY(90); "Green"; "")))))
The same version but with the below changes for your and others convenience.
=IF(Complete@row = 1, "Blue", IF(ISBLANK(Finish@row), "", IF(Finish@row < TODAY(), "Red", IF(Finish@row >= TODAY(45), "Yellow", IF(Finish@row <= TODAY(90), "Green", "")))))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
I was not able to get this to work.
Ok. Do you get an error message?
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
I have an automation setup to escalate to managers when a step goes beyond 2 days. I have that titled as Escalation for Purchasing, Escalation for Planning, etc. In my trial run, 3 out of 6 showed up as Reminder: New part number request log ( this is the name of the sheet) The only thing we could see was that the ones that…