I have dependencies enabled on my sheet and working days set for Monday – Friday. I am trying to write a formula to change the ball color based on the Hard Deadline. If hard deadline is within 5 working days then red; hard deadline is within 10 working day then yellow; over 10 working days green. My formula returns #UNPARSEABLE
=IF([Hard Deadline]@row - TODAY() < -5), "Red", IF(And([Hard Deadline]@row - TODAY() < 5, "Yellow"), "Green")))
I’ve also tried this formula and get the same #UNPARSEABLE
=IF([Hard Deadline]@row <TODAY(-5), “Red”, IF([Hard Deadline]@row <=TODAY(5), “Yellow”, “Green”))
I am new to Smartsheet and formulas, so any assistance I can get would be greatly appreciated.