I'm using resource allocation to calculate schedule duration but the schedule isn't updating to reflect the allocation.
Why didn't resource allocation (other than 100%) change task duration?
Hi Ami,
At this time, the duration of a task doesn't change based on the values in the Allocation % column, but this would be a great opportunity to submit a Product Enhancement Request to let our Product team know that you'd also like to have this functionality in Smartsheet.
As to the "why", please see Robin Sherwood's comment on this thread: https://community.smartsheet.com/discussion/allocated-time-versus-duration
same issue is for me. It would be smart to let culculatoin of the task duration from two columns like Workload and % Allocation. For example: if workload in 5d and allocation 50% -> Duration should be 10d and this 10d system should take to build Gant.
I have the same issue. It is sad to see that an issue identified in 2015 has not been implemented yet, despite the acquisition of 10,000ft.
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?