work week start Monday

i try to make filted "plan look ahead' its mean that i want to filter all task that will be next week.

the problem is samrtsheet start the week in Monday and in my place we work Sunday to Thursday


so how can i solve it ?

Best Answer

«1

Answers

  • Netanel yosef
    Netanel yosef ✭✭✭✭✭

    maybe you have othe solution

    i have a sheet with tasks fot current week and for next week

    and i want to display only the taks for current week Sunday to Thursday in card view

    every day in current week i need to see all current week tasks

  • Stefan
    Stefan ✭✭✭✭✭✭

    Hi,

    in your account settings you can define which days are workdays.

    Hope this helps

    Stefan

    Smartsheet Consulting, Solution Building, Training and Support.

    Projects for Processes and for People.

  • Netanel yosef
    Netanel yosef ✭✭✭✭✭

    i already set the working day but id i use in formula such as "weeknumber" the answer is not true

    its display the same work week for Sumday and Saturday before.

  • Stefan
    Stefan ✭✭✭✭✭✭

    Hi,

    seen internationally, the week number has an ISO definition (ISO week date - Wikipedia) but also different kind of counting in the world.

    Could your target "all tasks that will be next week" be translated to

    "all tasks started in the past + not completed OR starting within the next 10 (or other) days" ?

    I assume your look ahead should show what's up next and still ongoing during the specified time frame, right?

    This would relief you from "next week" as variable.

    Your filter in your sheet would look for rows, where

    • status is ongoing
    • OR
    • starting day is within the next 10 days

    Hope this helps

    Stefan

    Smartsheet Consulting, Solution Building, Training and Support.

    Projects for Processes and for People.

  • Netanel yosef
    Netanel yosef ✭✭✭✭✭

    hi,

    the sheet ment for two purposes:

    1. to display the tasks current week
    2. display the look ahead tasks for next week.

    i want to show it in card view that why i need dropdown for al days (sunday to Saturday ) and every day my employee update the date and i see it every day for each task.

    please see the sheet here in link

    https://app.smartsheet.com/b/publish?EQBCT=e47aa3db44124285bc34956b7506e218

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭
    edited 07/13/20

    Hi @Netanel yosef

    To add to Stefans excellent advice.

    You would need to define the specific days that should count. I think I have a formula in the archive. I'll get back to you!

    I hope that helps!

    Be safe and have a fantastic week!

    Best,

    Andrée Starå

    Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

  • Stefan
    Stefan ✭✭✭✭✭✭

    Hmmm, I hope you don't mind me asking, why you do not use the calendar view ? I ask because I would like to understand what you try to achieve from a business perspective.

    You get all the details when double clicking on the task.

    Greetings

    Stefan

    Smartsheet Consulting, Solution Building, Training and Support.

    Projects for Processes and for People.

  • Netanel yosef
    Netanel yosef ✭✭✭✭✭

    i want to know all tasks, employee and progress every day without clicking.

    this sheet show in dashboard in specipic screen in my office

  • Stefan
    Stefan ✭✭✭✭✭✭

    Hmm ok, I think you need your own calendar sheet.

    In the "Date" column (type date) you just need to enter the first day. "New week" is a checkbox column. And yes, you need 365 rows.

    In your existing sheet the helper column "Current work week helper" would have a formula like the following to get the week number belonging to the date in your "Date" column:

    =VLOOKUP([Created date]@row, {Date}, 2, false)

    {Date} = a cross sheet reference to the newly created sheet, where the complete columns "Date" and "Week number" must be selected.

    NOTE: Later changes to the sequence of the columns in the new sheet will damage the cross sheet reference.

    Your other helper column can probably be used without modification.

    Hope this helps

    Stefan

    PS: It's maybe a good idea to let Smartsheet know, that the calculation of the week number needs to be adjustable to the setting of your account. I you don't mind use the "Submit Product Enhancement Request" link on this page.

    Smartsheet Consulting, Solution Building, Training and Support.

    Projects for Processes and for People.

  • Stefan
    Stefan ✭✭✭✭✭✭

    PPS: If you use the formulas from my screenshot, replace all the ; with ,

    Greetings

    Stefan

    Smartsheet Consulting, Solution Building, Training and Support.

    Projects for Processes and for People.

  • Netanel yosef
    Netanel yosef ✭✭✭✭✭

    its make a circular referance in week number column.


    its make a problam if i add 365 rows beacuse we work only five days and i dont want see all 7 days.

    its seems somting that smartsheet cant support

  • Netanel yosef
    Netanel yosef ✭✭✭✭✭

    thanks its work i think...

    thanks all

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭

    @Netanel yosef

    Excellent!

    You're more than welcome!

    Glad you got it working!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.