Sign in to join the conversation:
Is there a way to create dependencies between multiple sheets in a report.
can you provide more details about what you are trying to do?
Hi...I have the same question...
I typically manage or consult on multiple interdependent projects. I've tried managing dependencies across projects in different ways but none of them have been super successful.
For example, Project A - call it Telephone installation - has a dependency on Project B - call it, Network Infrastructure upgrade. They are being managed as two separate workstreams because of their content and resources, but at some point, work on project A will stop if Project B hasn't reached a certain point (usually a milestone).
I would like to (in the best case) show the dependency actually in the dependent project so that Project B is late, the remaining tasks of Project A slip. Alternate would be okay if I could just report on the dependencies and highlight pending problems.
Any suggestions would be appreciated...
Rob
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?
Hi Team, I'm having trouble pulling data from a sheet into a dashboard, it won't let me select the tabs I'd like to use. Any tips?
I downloaded the request engagement template(s) and modified them for my business. Yesterday use of a contact list for notification was working, today it's not. I have recreated the workflow from scratch and added a new contact list column as suggested in blogs sequentially. Still not working. What does work is when I…