Hi,
When i report the schedule using Gantt View, the progress bar does not show.
Please clarify. What could be the reason>
Answers
-
Does the progress bar show on your source Sheet(s)? You will need to have project settings enabled and % complete column selected for it to show.
See this video for information on how to add this to a Sheet.
👨🏼💻 Dan Palenchar | School of Sheets Solutions Consulting | Smartsheet Aligned Gold Partner
If this helped, help me & the SSC by accepting and reacting w/ 💡insightful, ⬆️ Vote Up, and/or ❤️Awesome!
- 🆘 Smartsheet Consulting Inquiries: schoolofsheets.com/workwithus
- ▶️ Smartsheet Tutorial Videos: schoolofsheets.com/youtube
PS - If you have a follow up response tag me @SoS | Dan Palenchar so I get notified of your reply!
-
Thanks Dan.