Drop down options are N/A, Not Started, In Progress - On Track, In Progress - At Risks, Complete.
I want if children tasks are marked complete I want a % to calculate for those tasks marked complete minus N/A tasks.
Parent = 100% (correct)
Child 1 - Complete
Child 2 - Complete
Child 3 - Complete
Child 4 - Complete
Child 5 - Complete
Parent = 100% (correct)
Child 1 - N/A
Child 2 - Complete
Child 3 - Complete
Child 4 - Complete
Child 5 - Complete
Parent = 80% (This is incorrect and should be returned as 100%)
Child 1 - N/A
Child 2 - Complete
Child 3 - Complete
Child 4 - Complete
Child 5 - Complete