Hi, trying to get my Health formula to work for the status of tasks. Got the 'Blue' for Complete part of the formula correct, however when trying to build out the rest of the formula I keep getting syntax errors. The Health definitions the formula needs to perform are as follows. Any examples greatly appreciated.
GREEN:
Status is In Progress AND
% Complete is 1% - 99% AND
Completion Date (Planned) is > 60 days in the future
YELLOW:
Status is In Progress AND
% Complete is 1% - 99% AND
Completion Date (Planned) is < 60 days in the future
RED:
Status is Not Started OR
Status is In Progress AND
% Complete is 1% - 99% AND
Completion Date (Planned) is < 30 days in the future OR
Completion Date is in the past.