Good Smartsheet Community:
Are there Any Modification I Can Make to this Formula so that it skips Saturday and Sunday when Calculating My % Complete (Plan)?
Current Formula:
=IF(IFERROR(IF(AND(TODAY() >= [Start Date]@row, TODAY() <= [Finish Date]@row), ROUND(NETWORKDAYS([Start Date]@row, TODAY()) / Duration@row, 2), IF(TODAY() > [Finish Date]@row, 1, 0)), 0) > 1, 1, IFERROR(IF(AND(TODAY() >= [Start Date]@row, TODAY() <= [Finish Date]@row), ROUND(NETWORKDAYS([Start Date]@row, TODAY()) / Duration@row, 2), IF(TODAY() > [Finish Date]@row, 1, 0)), 0))
Thanks