Reaching out to see if you have any insight on something I am trying to do in Smartsheet
I have a cutover to production plan created and I want to automate the alerts when the predecessor task is complete, I want to an alert to go to the next task on the plan and alert the assigned to: that they can start their task. Is there a way to do this with Smartsheets without a heavy lift on setup?
Workflow Simplified Expectation:
- Task A is assigned to: John Smith
- Task B has a predecessor of Task A and is assigned to: Mary Johnson
- John Smith marks Task A as Status as Complete or Percentage 100%
Automation kicks off alert to Mary Johnson that they can start Task B