INDEX COLLECT FORMULA
Hello everyone,
I'm trying to do a workaround to avoid a circular reference that is happening when doing cross sheet formulas. For that purpose I'm building up a formula that brings to a column the end date of the last activity of the project
Activity Start Date End Date Activity 3 Date
-Project 1
Activity 1 01/01/22 05/02/22 26/06/22
Activity 2 06/02/22 25/03/22 26/06/22
Activity 3 25/03/22 26/06/22 26/06/22
-Project 2 Start Date End Date Activity 3 Date
Activity 1 01/07/22 25/09/22 09/12/22
Activity 2 26/09/22 25/11/22 09/12/22
Activity 3 26/11/22 09/12/22 09/12/22
How should I look up that Date?
Answers
-
I might be able to help but I'm not sure.
What formula(s) have you tried? I think an INDEX formula might work, but may need different functions instead of/in addition to COLLECT, but I would need a bit more detail. Are you trying to put the formula in your project sheet or the other sheet? And is that a sheet, report, etc.? Also do you need it to return that value once, or, if it updates, do you want that to be updated as well?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.8K Get Help
- 406 Global Discussions
- 219 Industry Talk
- 457 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 297 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!