Hoping to get some help with calculating health of a project. Here are my parameters:
Green: Status column is "Complete" or "In Process" or the Finish date is 7 days out or further.
Yellow: Status column is not "Complete", "On Hold" or "Cancelled", and the Finish is up to 1 day in the past.
Red: Status column is not "Complete", "On Hold" or "Cancelled", and the Finish was more than 1 day in the past.
Gray: Status column is "On Hold" or "Cancelled"
Blank: Health column is blank if the Status column and Target Finish columns are both empty.
If it's a parent row it shows a red health if any of the children rows under it have a red health, yellow health if any of the children rows show yellow (but not a red), and green if all children are green.