Hi,
Please I need your help. I have two date fields - Expected completion date and actual date completed. I'm trying to create a formula to say if actual date completed is greater than expected completion date, "Red", if actual date completed is blank, "Gray", else "Green"
My formula is: IF([Actual Date Completed]@row > [Expected completion]@row, "Red", IF([Actual Date Completed]@row < [Expected completion]@row, "Green", "Gray"))