Formula Help: Risk Flag based on End Date

itSmE
✭✭
Can someone help me create a formula based on end date
If EndDate is <TODAY and Status Does Not Equal "completed" Red Flag in Risk Column
TIA
Best Answers
-
Formula:
=IF(AND([End Date]@row < TODAY(), Status@row <> "Completed"), 1, 0)
Leroy Noriega | Smartsheet SME | Independent Smartsheet Consultant
Core App, Project Management and System Administrator Certified🏅
E: leroy.noriega@yahoo.com | Linkedin Profile
-
Perfect - thanks Leroy
Answers
-
Formula:
=IF(AND([End Date]@row < TODAY(), Status@row <> "Completed"), 1, 0)
Leroy Noriega | Smartsheet SME | Independent Smartsheet Consultant
Core App, Project Management and System Administrator Certified🏅
E: leroy.noriega@yahoo.com | Linkedin Profile
-
Perfect - thanks Leroy
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.5K Get Help
- 466 Global Discussions
- 156 Industry Talk
- 510 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 520 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!