I'm tracking all of the initiatives we have going on with a report to show a timeline of everything.
I'm wondering how best to show a project as cancelled.
I have sheet with projects linked and also a similar report.
I use the ghantt or timeline so we can visually see what's going on.
When a project is started and cancelled before the end, I want to keep it on the timeline to show what was being done at that time and to show that it was not completed.
How are you doing this? For now I've just removed it completely, but it's now a bare spot that looks like we were twiddling our thumbs for 100 days.
I would to show the progress it ended at. I don't think I am interested in showing the baseline end date, however I do see value to keeping it.