I'm trying to set up a project plan that has color indicators for the timeline: RED=past due, Yellow=due in the next 5 days, Green=due in the next 14 days, Blue=due later.
=IF([Due Date]2 < TODAY(), "Red", IF(AND([Due Date]2 >= TODAY(), [Due Date]2 < TODAY(+5))), "Yellow", IF(AND([Due Date]2 >= TODAY(), [Due Date]2 < TODAY(+14))), "Green", "Blue")
Thank you so much in advance!