Hello community,
I'm here again asking for help :)
I have a summary sheet that has status of all tasks across companies' project plans. I've got done the creation of a few cross sheet references for testing, these references targets those companies project plan sheets and its tasks progress percentage. The goal would be getting the task progress value changed as the dropdown menu with the company name is changed, changing the cross reference sheet value formula avoiding the creation of many summary sheets and then pulling the data to a dashboard.
Company1 Tasks
References for each company:
Dropdown menu (Column Project, row 6):
I tried to use the concatenate function but with no success, in the summary sheet I'm getting an #INVALID REF error. Formula used for it:
={Project6 + " - M365 Assessment"}
Thanks !
I'm open to suggestions 😉