We have a work around but it takes multiple helper columns and complex formulas.
You need WBS numbering
1
1.1
1.1.1
Sign in to see the current vote count, add your own vote, or leave a comment.
👍️ x 1,000. The template-based solution is appreciated, but clunky and high-overhead for what is really an essential function.
I'm not seeing anything recent about a possible ability to create a hierarchical Work Breakdown Structure (think org chart), then convert it to a project schedule sheet (parent and child). Would love to see that as a View, in addition to Card, Gantt, Grid and Calendar. The lack of a WBS that converts to a Grid View is a loss when moving from MS Project to Smartsheet. Does this have any hope of consideration?
I love that this creates the numbering I have been looking for sub-rows, but I have a question... If I have another sheet with an index collect formula can I just pull the parent row? My use case is an HR sheet with employee names and sub-rows of their certifications. I have another project sheet for employee health and I want to only pull the employee names over (parent row).
Please add a system column for WBS to give a true WBS without having to manually create one which is not always easy.
Hi Julie,
you are not alone; I asked the same question and no solution on this one.
Also tried to test out uploading the excel template with the WBS charts and failed. That's just not something that Smartsheet supports. The work around is to manually create the WBS visualization outside of Smartsheet and host the link in the dashboard that the end user can click on. I have hard time to believe this is not a feature in the Smartsheet.
Basically, we need to do it manually first even we have WBS created and manually update when there are any changes.
there is a Project with Work Breakdown Schedule (WBS) | Smartsheet I think it should be there for better visualization @Genevieve P. @Tom Zylstra
Work Breakdown Structure (WBS) - Column Formula Configuration - Page 3 — Smartsheet Community
The devs should be able to use Parent(WBS) to make this happen. Technically, this should not generate a cyclic error since a task should never be its own parent. I understand that the programming will flag it if we do it, but it should work if this field is added to the Project Settings as a special column - the same way it was done for Start Date, Duration, etc.
Most of the solutions on the web fail when you insert data or rows so be careful with them.
Our sheets & workspaces require many people to have Admin level capabilities, which means that when someone requests access to a sheet or workspace, that email is sent to every Admin. This causes confusion and higher risk of no access granted (because people have learned to ignore the emails) or the wrong level of access…
Today you can create a form and add logic. If that logic requires that requests need to be made for X days in the future you can add logic to help. For instance is the date requirement is not met you can hide fields so that information cannot be submitted completely. You can display a banner if date requirements are not…
I have project with automations sending emails based on specific criteria in the row. These automations are sent via email with a form to acknowledge receipt of the automated email. It would be fantastic if there was a way to track/ensure the email was sent without the need to send a copy of the automated email to my inbox.