Hello! I started using Smartsheet for project management and I'm having a hard time setting up schedule health. It is a bit time-sensitive as well. This is what I need:
I need some sort of formula that will automatically show schedule health based on the completion or non-completion of a task, using the Start Date, End Date, and Status columns. These are the criteria:
Green - on schedule (started on or before the start date/ended on or before the end date)
Yellow (2 work days passed from start date but it wasn't started/2 work days passed from end date but it wasn't ended)
Red (5 work days passed from start date but it wasn't started/5 work days passed from end date but it wasn't ended)
Gray (status is Not Started, Cancelled or On Hold)
Something along these lines. Could someone please help with this? Also note that if possible we will not use schedule delta.