Hey! So, I'm on a construction company, and I need to make a report that shows the tasks happening today
But I don't know how to show tasks that are not starting or finishing today, but are still in the process of completion.
With these filters, if a task started yesterday and is finishing tomorrow, it will not show on this Report
Thank you for the help!
(The Task column just makes sure it is a task and not a parent row)