Hello all,
Can anyone tell me why when importing an exported plan from Smartsheet into MS Project it places some of the %complete to 99% when it should be 0%? It is really annoying. I am currently trying it on a template plan.
Thank you in advance.
Hello Andresp,
The issue you are describing is a known bug with no currently known workaround. I have reported this instance to our development team for tracking.
Thanks!SchiffSmartsheet Support
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…