Hi guys, any advise on how works with % completed vs planned % completed as smartsheets only has column for % completed?, has anyone achieved to make a similar column for planned %?
Hello,
You can create a new text/number column in your sheet and format it for percent. Details on formatting columns for percent can be found in our Formatting Options help article.
If you need planned percent complete to be calculated for you, you'll need to create a formula in Smartsheet that does this. You can find the complete list of functions here: https://help.smartsheet.com/functions
How can I delete old sheets I no longer use from my account?
We want to implement single-sign-on at work and have received approval. However, our IT department wants all external partners to have/use Mayo credentials to log into Smartsheet. Not all of our external partners ever set foot on our campus and don't have our company credentials. I have a couple of questions. Has any other…
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…