All of my tasks are skipping over and not including this date (yesterday) in their calculations. I do not have this set as a holiday in the main settings. Is there a holiday/day off setting for the specific sheet?
Hi Jennifer,
There is! If you right-click any column header and select Edit Project Settings, then select Dependency Settings. Click the Edit button under Working Days and edit holidays here.
If you don't have holidays in the sheet, then you may have formulas that have holidays in their calculations. More info on different date functions can be found in our help center: https://help.smartsheet.com/functions
A few date functions that come to mine which allow you to include holidays are NETWORKDAY, NETWORKDAYS, and WORKDAY.
Shaine - thank you, thank you. There was an incorrect holiday in there. It fixed it. I love this forum!
Glad to help!
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?