Hello
Surprised to see users can enter over 100% in %Complete column.
I tried to constrain with pull downs but that isn't allowed for project dependencies...
Any thoughts?
-dp-
While the column name is "% Complete", the formatting is based on percent and there is no constraints in the column for range.
It struck me as odd when I first starting using Smartsheet, but I got used to it.
Maybe they will add data validation on Text/Number and this could be user defined, but I am not betting on it.
Craig
Thanks Craig
Odd indeed, especially since the column is part of project tracking dependencies!
Originally, the Duration column was not marked as special column -- it was just a Text/Number column with the Duration features. Maybe they will do the same with % Complete.
Could definitely use this. Currently I have a special auto-formatting rule set up to highlight when a % Complete cell is greater than 100%, but as all formatting rules create a processing burden on your sheets - it would be much nicer if this could simply be handled with a limit.
As long as the limit is not universally imposed, I'm all for constraints/validations on a column level (like restricted drop down lists)
I have had approval workflows and notifications built into a couple sheets for about a year now. In the past month, I am getting a lot of feedback saying people did not receive the email request for approval or notification email. It isn't all the time, just sometimes and there does not seem to be a pattern on which ones…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…