I'd like to know the best method for removing resources from Smartsheets without impacting the previous actual costs and future allocation to sheets
Hi Lifestyle PMO,
I think you may have to explain your question in greater detail to get the answer you're looking for.
Are you referring to removing resources from a project without affecting the already allocated tasks, hours, costs etc.?
Kind regards,
Chris McKay
Lifestyle,
If I understand the question correctly, when you remove a user from your account, the rows where they are or were assigned tasks, actions, projects do not change. Removal will only impact their access to the objects they were shared to.
I hope that helps.
Craig
Hi,
That is correct. If i was to remove a resource from a project would it affect the actual costs that were calculated previously when they were part of the project or will that data remain the same
Jags
Hi Jags,
To answer this, I'd need to understand how you are calculating those costs. Are you using SUMIF to look for a Resource value and then SUM all the costs associated? If so, then yes removing the resource will affect your calculations.
It's important to remember that you're not really "adding" a resource to a project. You have contact columns that are only useful for differentiating, calculating resource allocation % (which is still really flaky), sending notifications/alerts etc. You can also share sheets/workspaces with members of your Enterprise Smartsheet account, along with external collaborators.
If I unshare a collaborator for a sheet, the fact that they are included in the Resource column will not matter. They will still be there. The same goes vice versa when you remove someone from the Resource column but still keep sharing.
Hope this makes sense.
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…