Sign in to join the conversation:
Hi,
I am looking for a way to aviod the red man when a task has been completed. In my opinion the red man should disappear as soon as the task has been solved.
Thanks for your input.
Best Rgds,
Birgit
The issue appears when a task is completed prior to deadline.
What exactly is the "Red Man"?
Hi BTO
The Red man will disappear when the date is in the past as it is intended as a planning aid when resourcing the future. So maybe you have your start and finish date columns linked incorrectly?
Hope that helps?
RichardR
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…