I am trying the set up a dashboard using a rollup sheet.
I am trying to automate the start date so that it is always set to the 1st of the month or would it need to be manually changed every month?
Thanks
Dave
Give this a try...
=MONTH(TODAY()) + "/" + 1 + "/" + YEAR(TODAY())
What it does is displays the month for whatever TODAY is.
Then a /
Then 1
Then another /
And finally the year for whatever TODAY is.
Below is the result
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?