Hello!
I am wanting to put the gantt view of my project plan in a dashboard.
How do I go about doing this?
Hi,
You would use the report widget to show a report in Gantt view on the dashboard.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Hi Andree,
Thanks for your response. My gantt chart is in a sheet, not a report though. If I created a separate report, it doesn't look right. Do I need to do this extra step to pull into report form?
Happy to help!
To show the Gantt in a Dashboard, you need to create a report of the sheet or sheets that you want to display. Unfortunately, there isn't another way to do it.
What is it that doesn't look right?
Got it! Thank you, Andree.
This is an old thread but hope still active. When you create a gantt in report format you loose all of the dependencies and there appears no way to display them. Any advice. I really want to see the gantt the way it is displayed in the sheet ie. with dependencies and critical path.
seems odd that smartsheet has not added this functionality. Gantt chart should be able to be displayed with dependancies.
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?