Sign in to join the conversation:
Hello!
I am wanting to put the gantt view of my project plan in a dashboard.
How do I go about doing this?
Hi,
You would use the report widget to show a report in Gantt view on the dashboard.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Hi Andree,
Thanks for your response. My gantt chart is in a sheet, not a report though. If I created a separate report, it doesn't look right. Do I need to do this extra step to pull into report form?
Happy to help!
To show the Gantt in a Dashboard, you need to create a report of the sheet or sheets that you want to display. Unfortunately, there isn't another way to do it.
What is it that doesn't look right?
Got it! Thank you, Andree.
This is an old thread but hope still active. When you create a gantt in report format you loose all of the dependencies and there appears no way to display them. Any advice. I really want to see the gantt the way it is displayed in the sheet ie. with dependencies and critical path.
seems odd that smartsheet has not added this functionality. Gantt chart should be able to be displayed with dependancies.
I've done this a million times - create a report, separated by campus with a total $$. Then add it to a dashboard and make a graph. NOTHING is working right now when I try to do this. I get an error that the data cannot be charted. What the what? Help anyone? Is this a issue since they apparently changed something in the…
It does not matter which data I select, I am getting the error of Selected data cannot be charted. I even tried reusing a report that is producing a chart on a different dashboard, but I am unable to create new charts in a dashboard. Anyone have any ideas as to why?
I have inly one user in my trial account. When I am trying to upgrade to PRO plan it is defaulting for 2 users and not allowing me to upgrade the plan for only one user. Please help.