I would like to automate a due date of 5 weeks from the creation date unless the status is “On Hold”. Then the date should be blank. When the status changes from “On Hold” to "Open" then the date can be recalculated as above. Unclear how this can be done.
@Cath Jones
Change the column names to match your column names. Add the formula to your Due Date column - ensure that it is setup as a Date column.
=IF([Status]@row = "Open", [Created]@row + 35, "")
This is giving you a date if status = Open, or blank for any other status.
Hope this help!
I am using a large scale sheet to host a 23k+ row set of data. I imported the data into a table view. In a separate sheet, I am trying to establish a cross reference with my large scale sheet but I keep getting an error. I was just approved to use the large scale sheet, and I've never used it before. I know it comes with…
I have been using =IF(COUNTIF([Invoice Number]:[Invoice Number], [Invoice Number]@row) > 1, 1, 0) in order to check off a "duplicate" box and then added conditional formatting around that check box to visually assist staff with potential duplicate invoices being entered. It has recently stopped working for some reason and…
I’m trying to improve how we collect weekly status updates from task owners and would be interested in how others have solved this. Right now, each task has an owner and they type their weekly update into a Notes column. It works, but over time the Notes field becomes a running history and gets pretty unwieldy. What I’d…