I would like to automate a due date of 5 weeks from the creation date unless the status is “On Hold”. Then the date should be blank. When the status changes from “On Hold” to "Open" then the date can be recalculated as above. Unclear how this can be done.
@Cath Jones
Change the column names to match your column names. Add the formula to your Due Date column - ensure that it is setup as a Date column.
=IF([Status]@row = "Open", [Created]@row + 35, "")
This is giving you a date if status = Open, or blank for any other status.
Hope this help!
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…