I would like to automate a due date of 5 weeks from the creation date unless the status is “On Hold”. Then the date should be blank. When the status changes from “On Hold” to "Open" then the date can be recalculated as above. Unclear how this can be done.
@Cath Jones
Change the column names to match your column names. Add the formula to your Due Date column - ensure that it is setup as a Date column.
=IF([Status]@row = "Open", [Created]@row + 35, "")
This is giving you a date if status = Open, or blank for any other status.
Hope this help!
The below formula should give me the total price of a project filtering it by the panel name and the area. I do not want to include a certain supplier. Also Level 1 is totalling the child rows, so I want to filter that out as it give an inaccurate overall total of the price allocated to the panel and area. I can't figure…
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
I have an automation that runs every morning at 5:00 am ET that copies a row from one sheet to another sheet. I received this error in the Action block in the source sheet: Rows can't be added to the destination sheet because a column has the same name as a system column on the source sheet. Originally, I had a system Auto…