Enable Total Float to work with multiple predecessors.
Currently, Total Float will only calculate correctly when there is a single predecessor for an activity.
Yes, I would love to see this capability developed as well. Thank you!
This capability would be very useful for accurately showing which tasks are close to affecting critical path. As currently implemented, I don't see how TotalFloat can be used reliably since only the simplest of projects will not have some tasks with multiple predecessors.
This request was made almost a year ago and the discussion with moderator goes back even further. Does anyone know if its being worked on? Float/Slack is such a helpful/time saving piece of information when managing a schedule.
Another year down…almost. Any word? I had a cobble together my own highly specific code to very poorly approximate Total Float for my work. Our schedules are complex with heavy dependencies…and float is crucial for us.
Hope this gets resolved soon!
This is a much needed feature. Not sure I could recommend switching from Microsoft Project without this.