Question,
I am trying to create a Gantt chart that tracks a project in terms of days, not dates. For example, Task 1 will run from Day 1 to Day 5, Task 2 from Day 3 to Day 9 (instead of August 3rd- August 8th). Is there a way to do this?
Hello,
Tasks must be tracked using calendar days, but you can adjust the gantt timeline to display days 1-31 of the month and week numbers 1-52: https://help.smartsheet.com/articles/765755-modifying-project-settings#timelinedisplay