Hi Community Members,
I’m planning to migrate a project plan from Excel to Smartsheet. The sheet currently contains 600+ tasks, and many of the tasks are connected using predecessor/successor dependencies.
I would like to clean up the Excel file before importing it into Smartsheet by removing around 200 completed tasks.
However, I’m facing a challenge with the task dependencies. The predecessor/successor relationships are currently based on row IDs/numbers. When I delete the completed rows in Excel, the row numbers shift, which causes the predecessor references to become misaligned with the dependent tasks.
For example, if Task 50 has Task 45 as its predecessor, and I remove several completed tasks above Task 45, the row numbers change and the dependency references may no longer point to the correct tasks.
My questions are:
What is the recommended approach for migrating an Excel project plan with 600+ tasks and existing dependencies into Smartsheet?
Should I import the entire Excel sheet into Smartsheet first and then remove the completed tasks?
Is there a Smartsheet-supported way to preserve or remap predecessor/successor relationships when removing rows?
Is there a better way to restructure the Excel file before importing so that the dependencies remain intact?
Are there any best practices or tools/scripts that can help with this type of migration?
I want to avoid manually checking and recreating hundreds of dependencies after the migration.
Any guidance or recommendations from someone who has handled a similar Excel → Smartsheet migration would be greatly appreciated.
Thanks!
Jose