Hi,
This is our current formula for our progress bar:
=IF([Deployment Date]@row = "Cancelled", "", IF([Deployment Date]@row = "", "", IF(OR(COUNTIF([Copy Status]@row:[Code Status]@row, "Delivered"), COUNTIF([Copy Status]@row:[Code Status]@row, "--- N/A ---")) >= 4, "Full", IF(SUM(COUNTIF([Copy Status]@row:[Code Status]@row, "Delivered"), COUNTIF([Copy Status]@row:[Code Status]@row, "--- N/A ---")) = 3, "Three Quarter", IF(SUM(COUNTIF([Copy Status]@row:[Code Status]@row, "Delivered"), COUNTIF([Copy Status]@row:[Code Status]@row, "--- N/A ---")) = 2, "Half", IF(SUM(COUNTIF([Copy Status]@row:[Code Status]@row, "Delivered"), COUNTIF([Copy Status]@row:[Code Status]@row, "--- N/A ---")) = 1, "Quarter", IF(SUM(COUNTIF([Copy Status]@row:[Code Status]@row, "Delivered"), COUNTIF([Copy Status]@row:[Code Status]@row, "--- N/A ---")) < 1, "Empty")))))))
Currently, once something is marked as "Delivered", it completes the Progress Bar. But we currently just added the Option, "Using Code Bank", how can I add it in the formula for it to also complete the Progress Bar?