Hi, does anyone know if there is a way to generate a report to display only those activities/milestones on the critical path, rather than doing this manually through a check box filter. Thanks
Hi Dave,
Right now, the critical path is not available on reports - we're looking at ways to make it a criteria for reports, and I'll update this post if any progress is made.
Thank you!
Kara
Hi!
Any updates on this functionality?
Thanks,
Jose
Or suggested workarounds!
This is critical functionality. Is there any update on when will be available?
Echoing prior posts - providing the ability to generate a report (& dashboard) that flags critical path tasks would be quite useful.
Any update on when we could expect this to be made available?
This feature is available!
https://help.smartsheet.com/articles/504659-using-filters-to-show-or-hide-sheet-data?_ga=2.112568717.862956172.1552324686-238112621.1543429303
Hi, this article does show how to create a filter, but I don't see how to use that filter in a REPORT. I need the critical path to show in a report so it can be shown in a Dashboard.
Susanne
Hi everyone,
Please submit an Enhancement Request when you have a moment to have your vote addedA New Way to Submit Your Feature RequestsTo make your Enhancement / Feature Request count, send in the form above because there isn’t a guarantee, it will be registered otherwise.Original Post: https://community.smartsheet.com/announcement/new-way-submit-your-feature-requests
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå