Please see attached screenshot
In a separate field (that I haven’t yet created), I would want to know the % availability (based on 40hr work week) of each assigned resource based on each active request status.
Hi Darcie,
You might need to test this out a bit more extensively, but I was able to come up with a formula for resource allocation based on your sheet:
=SUMIFS([Est Hours]:[Est Hours], [Assigned To]:[Assigned To], "Person A", [Request Status]:[Request Status], OR(@cell = "In Process", @cell = "Approved By Mgr")) / 40
This summarizes all of the estimated hours of projects that have been approved and are assigned to "Person A." It then divides them by 40 to give you their percent allocation.
A few notes on this:
Let me know if you have any questions.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…