I am trying to give a percentage based on how 2 columns read. Column PassFailA and Column PassFailB. If both show Pass 100%, If A is Pass B is Fail or Vise Versa 50% and if both Fail 25%
Hello,
Thanks for the question. If I understand what you're looking to do correctly, this can be accomplished using a nested IF formula including the AND and OR functions. More on all of the available functions can be found here (https://help.smartsheet.com/functions), and we also have a blog post on how to build nested IF formulas which can be found here (https://www.smartsheet.com/blog/support-tip-build-nested-IF). Here's an example of how this could be written:
=IF(AND([Column PassFailA]@row = "Pass", [Column PassFailB]@row = "Pass"), 1, IF(AND(OR([Column PassFailA]@row = "Fail", [Column PassFailB]@row = "Fail"), OR([Column PassFailA]@row = "Pass", [Column PassFailB]@row = "Pass")), 0.5, IF(AND([Column PassFailA]@row = "Fail", [Column PassFailB]@row = "Fail"), 0.25)))
For this example I'm also using @row instead of the row's number within the cell reference. This will help make the formula more efficient as this sheet grows larger. More on @row can be found here (https://help.smartsheet.com/articles/2476491#row).
I've also included a screenshot of the outcomes for every scenario you listed. I'd also like to note that if either column is left blank, this formula will leave the % Column blank until both are set to either "Pass" or "Fail".
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…