Based on the below screenshots, I am looking for a formula to SUM the FEE column only if the Project Stage column is equal to "Paid". I feel I am close to solving the formula. Any suggestions will be greatly appreciated.
Try
SUMIF([Project Stage}:[Project Stage},"Paid", FEE:FEE)
You could try something like this. Not very elegant though. I may look at this a bit more after work .
=SUMIF([Project Stage]2:[Project Stage]19, "PAID", FEE2:FEE19)
Ah, sorry... Looks like rjudenberg has the answer.
With one minor adjustment rjudenberg had the right answer:
SUMIF([Project Stage]:[Project Stage],"Paid", FEE:FEE)
His close brackets on the Projects Stage range were curly brackets which could cause some confusion for Smartsheets and curly brackets tend to point to a range in another sheet.
This worked perfect, because I am linking to another page the formula came to be this:
=SUMIF({Mimi's Project Management 2018 Range 7}, "Paid", {Mimi's Project Management 2018 Range 3})
and
=SUMIF({Mimi's Project Management 2018 Range 7}, "Invoiced", {Mimi's Project Management 2018 Range 3})
Thank you rjudenberg!
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…