I have a sheet with thousands of projects. When a project is finished there is a cell that automatically calculates the turnaround time. There is also a column for the date the project was finished. The projects are not ordered by date. On another sheet I need to calculate the average turnaround time for a given month for projects finished in that month. Does anyone know what formula I can use to do this in smartsheet?
Using
(SUMIF(Month([FinishedDate]) = 1, TurnAroundTime:TurnAroundTime)/Countif(Month([FinishedDate]) = 1)
This will add all of the turn around times and then divide by the number of projects that finished in that month. You'll need to get fancier if you need to look at year, but then you just need to use SUMIFS with Month and Year functions.
All fake code, but it should get you started with the correct functions.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…