is there an ability to set a conditional format based on two columns in the same row:
completed (column) date is later than the due (column) date – the cell turns red
completed date entered is before (or after) today's date
Yes, there is! Thought its kind of hidden. After you set up a conditional formatting you have to click on the arrow to the left of the condition and add another condition. See Screenshot.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…