I accidentally deleted the %complete column in my smartsheet. How do I insert it back into the project? I don't see a quick way of doing this.
Hi Andrew,
While it won't bring back any of the data you had in the column, you can simply add a new % Complete column, navigate to the Project Settings window (via the gear icon in the top right) and then selecting the column you just created from the dropdown list under % Complete column.
Kind regards,
Chris McKay
Hi Andrew and Chris,
I also wanted to let you know that you can always write into Support and ask for a checkpoint of your sheet; an agent will be glad to send you this in Excel format and it should have data that you can copy and paste back into your sheet.
Please note that the checkpoints we have available only contain the grid data and Comments (on the second page of the workbook) and won't be as comprehensive as any backups that you make as your backups will also include a compressed file of attachments. If you haven't yet started performing backups, I recommend doing so to assist in case of future accidental changes or deletions. If needed, instructions for this are available in our help article on Backing up your data (http://help.smartsheet.com/customer/portal/articles/506499-backing-up-your-data)
I would also highly recommend setting up some periodic recurring backups via the steps at our Help Center here.
AlisonSmartsheet Support
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…