I accidentally deleted the %complete column in my smartsheet. How do I insert it back into the project? I don't see a quick way of doing this.
Hi Andrew,
While it won't bring back any of the data you had in the column, you can simply add a new % Complete column, navigate to the Project Settings window (via the gear icon in the top right) and then selecting the column you just created from the dropdown list under % Complete column.
Kind regards,
Chris McKay
Hi Andrew and Chris,
I also wanted to let you know that you can always write into Support and ask for a checkpoint of your sheet; an agent will be glad to send you this in Excel format and it should have data that you can copy and paste back into your sheet.
Please note that the checkpoints we have available only contain the grid data and Comments (on the second page of the workbook) and won't be as comprehensive as any backups that you make as your backups will also include a compressed file of attachments. If you haven't yet started performing backups, I recommend doing so to assist in case of future accidental changes or deletions. If needed, instructions for this are available in our help article on Backing up your data (http://help.smartsheet.com/customer/portal/articles/506499-backing-up-your-data)
I would also highly recommend setting up some periodic recurring backups via the steps at our Help Center here.
AlisonSmartsheet Support
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…