Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
I am trying to work on my sheet to get the % Completed to be automated. How can I go about doing this?
Hi there!
I am fairly new to Smartsheet as well and I used logic similar to excel and did a countif and then divide it by a total count. I used checked boxes for each step and it would update my % Complete for me.
Here is the formula that I utilized, but there might be something simpler that I am not aware of.
=(COUNTIF([Scope Complete]2:Done2, <>0) / (COUNT([Scope Complete]2:Done2)))
Good Morning,
I just tried it and it is not working for what I am looking to do I have target date and completion date. When I change the information in the formula tabs it comes up with the Unparsable error
I wasn't using dates -but you could create a column that gives you the total days and the total remaining days based on the target. I am sure you could do this in a formula as well. My formula was looking to see if multiple columns were greater than 0.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…