I'm new to Smartsheets and I'm trying to figure out how to do an IF([Response]3="Yes", VLookup formula linked to a reference data sheet. I've tried various ways to input and always get Unparseable. Any help is appreciated!
You have to create that reference in the little drop-down data that appears while typing in your formula. Then you will select your range and finish the formula.
See screenshot below for reference.
But my initial IF is based on a field on my current sheet then I lookup my reference sheet hours based on that answer - first true then false.
You should be able to apply the same methodology to set your vlookup... =if(x=x, Vlookup( -- choose the external reference when you start typing this.
See screenshot below.
I know I'm not doing this right - LOL. Here is what I have and still not working - I feel like I'm missing the logical expression in my referenced sheet, but I'm just not sure...
=IF([Office Test Lab]1="Yes", VLOOKUP({Apexstamator Reference Data Range 2}"Lab Test Office Yes",{Apexstamator Reference Data Range 1}, 2), {Apexstamator Reference Data Range 3})
Try troubleshooting by comparing your lookup to the instructions found on the function post itself. Or the limitations as seen on the second article.
Those might give you some clues as to how you should set it up.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…