Hi,
I would like to change a symbol cell based on the status of a predecessor completion status i.e.
"If a predecessor completion status is 100% then the status of this raw should change".
Hi Shanon,
You can do this by creating an IF formula in the symbol column. To get a better sense of how this works, I recommend taking a look at this blog post:
https://www.smartsheet.com/blog/support-tip-automate-RYG-balls
There are also a few posts here in Community with specific examples that you can draw on.
https://community.smartsheet.com/discussion/automate-ryg-project-tasks
https://community.smartsheet.com/discussion/if-and-formula-rgy
Happy formula building!
-Gwyneth
Sorry to be the bearer of bad news, but despite the tutorials/threads linked to above, the answer is no.
There is no way to reference the values in the Predecessors column in any meaningful way.
An IF statement in the Symbol column will only be useful if your tasks are Children of the Predecessor. There is also the added complexity of SS, FS and FF relationships to be considered.
Building nested IF statements with additional identifier columns et. will make a complex web of formulas that will almost certainly fall over in practice.
Kind regards,
Chris McKay
Apologies, I didn't look carefully enough at your request Shanon—it's more complex that my solution solves for. Thanks for chiming in Chris.
Regards,
Gwyneth
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…