Can anyone tell me what I am doing wrong here? I am trying to automate RYG balls from a % column.
=IF([% Complete]3 < 50, "Red", IF([% Comlete]3 = 100, "Green, IF([% Complete] >50 AND <100, "Yellow")
=IF([% Complete]3 < 50, "Red", IF([% Complete]3 = 100, "Green, IF([% Complete] >50 AND <100, "Yellow")
Corrected spelling error!
Smart sheet displays the percentages as such, but in reality the backend is reading a decimal. When referencing perecentages in formulas you should use .5 for 50% and 1 for 100%. SO your formula would look like this...
=IF([% Complete]3 < .5, "Red", IF([% Complete]3 = 1, "Green, IF([% Complete] >.5 AND <1, "Yellow")
Thanks Mike, but there is still something wrong: unparseable!
I have tried a dozen times with the same results!
Duh I should have looked more carefully! And statements should be made as indicated below...
=IF([% Complete]3 < .5, "Red", IF([% Complete]3 = 1, "Green, IF(AND([% Complete]3 >.5, [% Complete]3 <1), "Yellow")))
You also didn't have enough closing parenthesis.
Maybe I have been staring at this too long! It still doesn't work. Did it work for you?
YOU are a peach, by the way. Thanks for helping.
Are you getting unparseable still?
=IF([% Complete]3 < .5, "Red", IF([% Complete]3 = 1, "Green", IF(AND([% Complete]3 >.5, [% Complete]3 <1), "Yellow")))
Green was missing a closing quotation mark!
Yes
#baldfromtearinghairout
Did this one work?
Green was missing a quotation mark!
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…