I am having a hard time putting together the formula for my Health Column- RYGB Ball. I need the formula to be the following. Any chance some one could help put this formula together for me? Thanks
=IF(Status@row = "Not Started", "", IF(AND(Status@row = "In Process", [Due Date]@row <= TODAY()), "Yellow", IF(AND(Status@row = "In Process", [Due Date]@row > TODAY()), "Green", IF(Status@row = "Complete", "Blue"))))
Out of curiosity... Were you wanting to do anything with the "Red"?
Thank you Paul for this formula. This is great!!!! You saved me so much time from trying to figure this out. I need to be able to select Red manually for the milestone plan that I am working on. I tested it out and see that I can override the formula where I need to.
The only downside to manually selecting "Red" is that it will erase the formula. It's as simple as Copy/Paste to get it back in there, but I'm an automation junkie. I like to be able to input as little as possible and let the sheet do the rest. Haha
Glad I could help though.
Maybe your right and I should add an At Risk status so I can keep it automated. I updated the formula to include Red and it worked. Thanks again
=IF(Status@row = "Not Started", "", IF(AND(Status@row = "In Process", [Due Date]@row <= TODAY()), "Yellow", IF(AND(Status@row = "In Process", [Due Date]@row > TODAY()), "Green", IF(Status@row = "Complete", "Blue", IF(Status@row = "At Risk", "Red")))))
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…